71703: Flooring Replacement
Scope of Project: Replace existing 15 year old carpeting
Budget: $400,000
Target Completion Date: 2007-08
Point Persons: Director of Facility Planning - Mike Adams, Director of Maintenance & Operations - Larry Wise, and Custodial Supervisor - Tony Risch
Committee: none
UPDATE
February 2008 - Planning is continuing to determine costs for the replacement of flooring in the PE and the Center for the Visual & Performing Arts buildings.
December 2007 - Flooring replacement in the Career Center, Financial Aid, and hallways has been completed. Flooring in the Couseling Office is scheduled for completion during the current fiscal year. Classrooms and offices of MacMillan Hall, along with other building on campus will be sequenced to coincide with renovation projects in those buildings in order to minimize disruption to classes and district operations.
August 2007 - Carpeting has been replaced in the President's Office and Board room.