717010: Disabled Access Improvements
Scope of Project: Meet state and federal regulations regarding accessibility.
Budget: $250,000
Target Completion Date: Phase 1 projects: August 2009
Phase 2 projects: August 2010
Phase 3 projects: May 2012
Point Persons: Meridith Randall, Vice President of Education and Student Services, Mike Adams, Director Facilities Planning
Committee: none
UPDATES
December 2010 - All Phase 1 and 2 tasks are complete. Phase 3 items that were incorporated into the Maintenance Building/Modular Relocation project are complete. Phase 3 projects in the Lowery building and/or associated with the new Library/Learning Center will be implemented as those projects are completed.
December 2009 - Phase I projects are complete, including the addition and updating of the automated doors and handicap seating in the Little Theatre. Also completed are an ADA compliant crosswalk and ramps to the SSU building. Planning for Phase 2 projects will continue and be implemented when scheduling permits. All Phase 1 and 2 projects are planned for completion by August 2010. Phase 3 projects will be incorporated into various larger projects and will be completed when those projects are implemented.
July 2009 - The final projects for the Phase I items is scheduled for completion in August 2008. Phase II will be implemented by August 2010.
March 2008 - The Disabled Access Committee has begun scheduling meetings to review and prioritize the assesment report that was generated in 2004 by TLCD Architecture