General Info > Measure W Bond > Projects > 717010: Disabled Access Improvements

717010: Disabled Access Improvements

 

Scope of Project: Meet state and federal regulations regarding accessibility.

Budget: $145,143

Completion Date:             Phase 1 projects: August 2009

                                        Phase 2 projects: August 2010

                                        Phase 3 projects: May 2012

Point Persons: Mike Adams, Director Facilities Planning

Committee: none

UPDATES

December 2013 - Upon completion of the ADA signage in the Lowery Student Center during the Fall of 2013, all ADA projects identified in the District's assessment and mitigation plan are complete.

June 2012 - This project is nearing completion with remaining ADA project expenditures to be incorporated within other projects. The final phase of this project addresses access to the Business Office and will be completed in July 2012.

September 2011 - All Phase 1 and 2 tasks are complete. Phase 3 items that were incorporated into the Maintenance Building/Modular Relocation project are complete. Phase 3 projects in the Lowery building and/or associated with the new Library/Learning Center are being implemented as those projects are completed. There are no further changes to this project at this time.

December 2010 - All Phase 1 and 2 tasks are complete. Phase 3 items that were incorporated into the Maintenance Building/Modular Relocation project are complete. Phase 3 projects in the Lowery building and/or associated with the new Library/Learning Center will be implemented as those projects are completed.

December 2009 - Phase I projects are complete, including the addition and updating of the automated doors and handicap seating in the Little Theatre. Also completed are an ADA compliant crosswalk and ramps to the SSU building. Planning for Phase 2 projects will continue and be implemented when scheduling permits. All Phase 1 and 2 projects are planned for completion by August 2010. Phase 3 projects will be incorporated into various larger projects and will be completed when those projects are implemented.

July 2009 - The final projects for the Phase I items is scheduled for completion in August 2008. Phase II will be implemented by August 2010.

March 2008 - The Disabled Access Committee has begun scheduling meetings to review and prioritize the assesment report that was generated in 2004 by TLCD Architecture

Created: August 29, 2007 @ 01:03 PM
Last Modified: February 04, 2014 @ 11:37 AM

 





  Copyright © 2001 - 2010     Mendocino College is not responsible for third party content.