717120-717160: Re-roofing Projects
Re-roofing Schedule in Exel
Scope of Project: Re-roof of 7 buildings on Ukiah campus:
- Project No. 717120 Agricultural Headhouse and Potting Shed
- Project No. 717130 Center for the Visual and Performing Arts
- Project No. 717140 Child Care Center
- Project No. 717150 Physical Education Building and Gymnasium
- Project No. 717160 Vocational Technical building
Cost: $967,476
Target Completion Date: October 2007
Contractor: Solano County Roofing
Point Person: Director of Facilities Planning Mike Adams
UPDATES
April 2008: A proposal from a local roofing company to repair the small, flat roof, located in the hallway connecting the PE locker area to the Gym, has been accepted and work will be completed by June 30, 2008.
January 2008: Notices of Completion have been recorded for the re-roofing of the Voc-Tech building, Agricultural Headhouse and potting shed, Child Care Center, Center for Visual and Performing Arts, and the Physical Education building and gymnasium.
The small, flat roof, located in the hallway connecting the PE locker area to the Gym has been identified as leaking and is scheduled for repair later this spring.
December 2007: Re-roofing of the Voc-Tech building, Agricultural Headhouse and potting shed, Child Care Center, Center for Visual and Performing Arts, and the Physical Education building and gymnasium is complete. The project was accepted by the M-LCCD Board of Trustees on December 12th.
October 2007: Crews are currently working on finishing detail work, including downspouts and gutters. Recent rain delays have pushed the anticipated completion date to November 2007
September 2007: All materials have been delivered to MLCC for completion of roofing project. Date for completion of all six buildings within this project is expected to be mid-October, 2007
August 29, 2007: Both PE 1 Bldg. and Gym have been made watertight. Materials are on site for all other buildings. Fine Arts metal roof material is being installed. Voc/Tech building is complete (punch list to be developed).
College Re-roofing Project Ahead of Schedule (7/20/07 news release)


Created: July 20, 2007 @ 07:21 PM
Last Modified: September 23, 2008 @ 12:52 PM