General Info > Measure W Bond > Projects > 717210: Maintenance/Warehouse

717210: Maintenance/Warehouse/East Campus

Scope of Project: Construction of a new building on the Ukiah Campus that will relocate the Maintenance and Operations department out of the existing Agriculture and Voc/Tech buildings, relocation of the SSU building, a new parking lot, and site preparation for the relocation of the modular buildings currently located in the Quad area.

Budget: $4,712,064

Completion Date: February 2, 2011

Lead Person: Mike Adams, Director of Facilities Planning, Steve Oliveria, Director of Maintenance and Operations 

UPDATES

June 2012 - Equipment for the facilities has been purchased and maintenance equipment selection and purchases are now complete.

December 2011 - Equipment for the facilities has been purchased and maintenance equipment selections are in the final stages.

March 2011 - The Maintenance/Warehouse project, including the parking lot, site preparation, and utilities for the East Campus project, is complete. Equipment for the facilities has been purchased and final selections on maintenance equipment is in the planning phase. 

December 2010 - The Maintenance/Warehouse project, including the parking lot, site preparation, and utilities for the East Campus project, is scheduled for final completion in February 2011. Beneficial occupancy took place during the Winter break.

September 2010 - This project, including the parking lot, site preparation, and utilities for the East campus project, is scheduled for completion in November 2010.

December 2009 - The Maintenance/Warehouse/East Campus development project, including the parking lot, site preparation, and utilities for the East campus project, has been awarded. Relocation of the SSU building was completed during the winter break. The moving of the current campus quad buildings to their new location on the east campus is scheduled for the summer of 2010.

July 2009 - Plans for the Maintenance/Warehouse have been finalized. The project will be bid in three phases:

1) Maintenance/Warehouse and site work

2) East campus portable relocation

3) Sonoma State University

June 2008: Project details are continuing to be developed by the planning committee. A Preliminary Design project estimate has been conducted and is within the project budget. The project location is being reviewed to confirm the project is consistent with the overall campus long range master plan. The planning process is temporarily on hold while the project location is being confirmed. 

February 2008: A preliminary design footprint and exterior elevations have been the main focus at this time. The soils investigation has been conducted by LACO Associates. The project could go out to bid in the Summer of 2008, with completion possible in 2009.

September 2007: Meetings were held with TLCD Architecture to finalize the projected project scope and to finalize the architectural agreement. It was agreed that a local metal building contractor will be utilized to assist in developing the project specifications and budget.

August 2007: Modified contract from TLCD Architecture has been submitted to District and project is awaiting approval to proceed.

January 16, 2007: The green light has been given to form a committee to begin the planning and implementation of the new Maintenance/Warehouse to be located on the Ukiah Campus, part of the college’s Master Plan.

Created: January 24, 2007 @ 09:16 AM
Last Modified: August 29, 2012 @ 10:38 AM

 





  Copyright © 2001 - 2010     Mendocino College is not responsible for third party content.